Shock wave measuring while working the tunnel for the needs of the river Cehotina flow direction change
This paper deals with the problems related to the working of the Veliki Pliješ tunnel for the needs of the river Ćehotina flow direction change. The tunnel was worked by using the method of drilling-blasting operations. The parameters of blasting while working both the canal and the tunnel pipe are shown in the first part of the paper. Some of valid criteria related to building protection from the seismic effects of blasting, as well as the results of seismic observation for the conditions of blasting operations while working the V.Pliješ tunnel, are shown in the second part of the paper.